QUESTIONS AND ANSWERS

Published: 2014-01-03
Last updated: 2022-03-11


In this "Questions and Answers" section I publish the questions you submit, together with the answers that make the most sense from my point of view.

Lower down, on this page, you find the form for your questions and submission.

Jump directly to the form.

Submitted questions and answers


Question 1:   What are the objectives of project identification?

Answer:   In an organization doing business with projects there is a strategy in place about what kind of projects they want to undertake. Based on that strategy, they will be able to identify possible projects which support that strategy. Additionally, they have a set of criteria that helps them to select those projects that fit best to their strategy: in terms of expertise, potential growth of their business, profit, etc.

Example: Company A's strategy is to do their business with constructing office buildings. So, they will mainly scan the market for potential customers who need to create or expand office space, but will not look for customers who want to build new private homes. In case they have the opportunity to undertake two similar projects, but do not have enough resources to do both, they might select that project which turns in the higher profit.

Please refer to Project Selection and Project Definition for further details.


Question 2:   I received seveal questions regarding project selection or methods and tools for project selection. After some careful consideration, I decided to create a sub-section, A Project Selection Case, where I give some examples and discuss the methods and tools which I introduce in section Project Selection.


Question 3:   What are the objectives of project planning?

Answer:   The project management team needs to be in control of all project activities. Therefore, they need a plan of all those activities. So, the objectives of project planning are to create this plan:

  • PBS - what are the project results and its components,
  • WBS - what are the activities to be done in order to achieve those results,
  • Network diagram - logical sequence of all activities,
  • Gantt chart - time schedule for the activities,
  • Resource plan - who has to carry out those activities,
  • Cost plan - how much does the project cost.

Please refer to Project Planning for further details.


Question 4:   Why is teamwork important in all phases of a project?

Answer:   For most - if not all - projects we need the contributions of people with different background and different expertise. They have to work together in order to create the project results. Thererfore, it is worthwhile to take care of how project teams develop and what their team dynamics are.


Question 5:   What process would you follow to update a schedule plan?

Answer:   Strictly speaking, I would follow the same process as used when setting up the project schedule the first time:

  • First step - start with the milestone plan and update it if necessary.
  • Second step - check if you need to change and update the network diagram i.e. the logical sequence of work packages / project activities.
  • Third step - update the Gantt chart i.e. the time schedule of all work packages / project activities accordingly.

Please refer to Project Schedule for further details.


Question 6:   Why do we need to include effort, duration and resource cost into our cost estimation?

Answer:   in Planning phase, we would like to obtain a complete plan of the project scope (provided by the WBS), the project schedule (provided by the network diagram or the Gantt chart) and the project cost (provided by the cost plan).

For the project schedule, we need to estimate the duration of each work package. Often, we assign several colleagues who have different skills and different hourly or daily rates to a work package. Therefore, it is necessary to estimate the work package effort separately.

For example:

There is a work package WPx, with two colleagues, Adam and Ben, working on it. Their resource costs are

  • Adam is electrical engineer with a daily rate of USD 800,
  • Ben is electrical technician with a daily rate of USD 560.

We estimate the duration of WPx to be 5 days, Ben working on WPx for the five days straight. Adam is helping him for only 2 days. This will lead to an estimated duration of 5 days and a total effort of USD 4,400.

Adam and Ben might also need cables, switches and sockets which amount to USD 200. So, the total cost of WPx will be USD 4,600.

For the cost plan, we need to know when the different types of cost will be accrued or booked to the project. Thus, we add information about the time of accrual of each cost type. In our example above this might be

  • cost of material: at the start of WPx
  • cost of manpower: at the end of WPx




35+ templates, tools, and checklists in one set

To save you time in your daily work as a project manager, I packaged more than 35 project management templates, tools, and checklists into one zip file.

  • You un-zip it, and you get all items in formats you can edit to your requirements.
  • They strictly contain only standard functionality and no macros or other code.
  • You are allowed to use your logo.
Templates & Checklists for Implementation and Closure Phase
for only
or click here for more info.



Submit your question

If you have a question for any topic on this website, enter it into the following form and submit it.

Within a day or two, you will find your question and my answer on this page.

Your question

Please note that all fields with an asterisk must be filled in.

Please enter the word below.


  






Return from "Questions and Answers" to Home Page





Your Comments

Have your say about what you just read! Leave me a comment in the box below.
Enjoy this page? Please pay it forward. Here's how...

Would you prefer to share this page with others by linking to it?

  1. Click on the HTML link code below.
  2. Copy and paste it, adding a note of your own, into your blog, a Web page, forums, a blog comment, your Facebook account, or anywhere that someone would find this page valuable.